Construction Planning and Management Part 1

Construction Planning and Management Part 1

Construction Planning and Management Part 1

Category –CE Online Test

Telegram-Join Us On Telegram

Attempt Free Construction Planning and Management Part 1 Here. Read The Important Engineering MCQ From Below.

Q1. Which of the following is not another name of Hoe ?
A. Backhoe
B. Back-shovel
C. Pull shovel
D. Trenching machine

Answer : D

Q2. Which of the following is not an excavating, equipments ?
A. Power shovel
B. Scraper
C. Dragline
D. Hoe

Answer : B

Construction Planning and Management Part 1

Q3. The effectiveness of explosion during tunnelling increases by the process of
A. Squibbing
B. Stemming
C. Priming
D. Firing

Answer : B

Q4. Which of the following is not needed in a large store ?
A. Trolley
B. Fork lift
C. Gravity feed system
D. None of these

Answer : D

Construction Planning and Management Part 1

Q5. Bar charts are considered suitable for
A. Major projects
B. Minor projects
C. Large projects
D. All of these

Answer : B

Q6. PERT is
A. Activity oriented
B. Event oriented
C. Time oriented
D. Resources oriented

Answer : B

Construction Planning and Management Part 1

Q7. In PERT technique, completion of an activity is called
A. Head activity
B. Head event
C. Tail Activity
D. Tail event

Answer : B

Q8. Critical path
A. Is always longest
B. Always shortest
C. May be longest
D. May be shortest

Answer : A

Q9. The effect of network compression is increase in the
A. Total cost
B. Direct cost
C. Indirect cost
D. Overheads

Answer : B

Construction Planning and Management Part 1

Q10. Size of a dragline is indicated by the size of
A. Bucket
B. Dipper
C. Cab
D. Boom

Answer : A

Q11. Material used for the construction of load bearing piles is
A. Wood
B. Concrete
C. Steel
D. Any of these

Answer : D

Construction Planning and Management Part 1

Q12. The amount saved as depreciation reserve fund will be termed as
A. Operating cost
B. Profit
C. Loss
D. None of these

Answer : D

Q13. PERT technique of network analysis is mainly useful for
A. small projects
B. large and complex projects
C. research and development projects
D. deterministic activities

Answer : C

Construction Planning and Management Part 1

Q14. Which one of the following is not the excavating and movinig type machine ?
A. Dragline
B. Scraper
C. Buldozer
D. Dump truck
Add to Fav View Answer up 20 Down -12
Explanation:-
Answer : D

Q15. Select the correct statement.
A. Activity arrows in a CPM network are drawn to scale
B. The tail of an arrow represents the finish of an activity
C. Arrow bead represents the start of an activity
D. none of the above

Answer : D